David D. Lawrence Convention Center
Pittsburgh, Pennsylvania (USA)
Project Description
- Steel construction of more than 16,000 tons designed to mimic a large ship.
- The project, due the unique geometry of the roof structure (composed of 3D trusses and pre-tensioned cables) presented several challenges both in terms of fabrication and erection.
- This project is the largest in the world who received a gold LEED (green building) board.
- Building covering an area of 1.2 million sq ft.
Description of services provided
- Fabrication Engineering: Concept and design of all complex connections for the detailing of the steel structure. Coordinated the design of connections with Design Engineers, Architect and Erection team.
- Construction Engineering: Design and development of the erection procedure.