Énergir – Louis-Bisson Bridge Gas Line Supports
Laval (QC)
Montreal (QC)
Project Description
As part of the project to replace the existing bridge deck by the MTQ, Gaz Metro ordered a study to replace the supports of the suspended gas pipeline to the existing bridge deck. Instead of being suspended to the concrete deck, new supports are to be attached to the steel beams of the bridge. Our design also included the implementation of a fall protection system.
Description of services provided
- Inspection of existing pipe supports;
- Preparation of plans and specifications for the modification of the supports.